Equinox Gold Announces Full-Scale Construction of the Aurizona Gold Mine

Download PDF

Equinox Gold Corp. (TSX-V: EQX, OTC: LWLCF) (“Equinox Gold” or the “Company”) is pleased to announce that the Company’s Board of Directors has approved the start of full-scale construction at the Aurizona Gold Mine (“Aurizona”) in Brazil. All dollar amounts shown are in United States dollars.

Early works construction has been underway at Aurizona since the third quarter of 2017. The project is advancing well and remains on track to pour gold by late 2018. Activities to date have focused on detailed engineering work, raising the existing tailings facility, refurbishment of existing plant infrastructure, civil earthworks and pouring foundations to prepare for installation of new plant infrastructure, installation of new administrative buildings and ordering long-lead items.

Equinox Gold’s new website at www.equinoxgold.com includes a photo gallery that documents construction progress with periodic photo and video updates.

Construction Milestones Achieved to Date

  • Mills ordered with delivery expected in the second quarter
  • Detailed engineering underway in Belo Horizonte, Brazil
  • Civil works (concrete) contract awarded
  • Owner’s team in place
  • Significant refurbishment completed on existing plant infrastructure
  • Electrical substation upgrades commenced with parts ordered and a contractor selected
  • Completion of the first tailings storage facility raise nearly complete
  • Mill foundations underway
  • Completion of the thickener underway

“With expansion permits, full construction funding and the new Equinox Gold Board of Directors in place, we have received approval for full-scale construction at the Aurizona Gold Mine in Brazil,” said Christian Milau, CEO of Equinox Gold. “This will be a milestone year for Equinox Gold as we advance Aurizona and transition the company from a developer to a meaningful producer, with more than 135,000 ounces of annual gold production expected from Aurizona.”

“The Aurizona project has been significantly advanced and de-risked over the past few months with early works construction and critical path activities,” said David Laing, COO of Equinox Gold. “The tailings dam raise is nearly complete, the mills are ordered and significant civil earthworks has been completed in preparation for installation of the mills and other new plant infrastructure. We look forward to reporting on construction milestones as we advance toward our target of pouring gold in late 2018.”

Equinox Gold’s Board of Directors has approved a total project budget of $146 million for full-scale construction, which includes all working capital and a 12% contingency. Approximately $25 million of this budget was spent in 2017 during early works activities and the project remains on schedule and on budget. Aurizona construction is fully funded with Equinox Gold’s existing treasury and an $85 million secured project credit facility, from which the Company has drawn $15 million to date.  

Tailings Facility Raise

The existing tailings facility is being raised to support expanded throughput to 8,000 tonnes per day (“tpd”). The raise is being executed by the Engeterra-Nazaré consortium under the supervision of the structure designers BVP Engenharia. The tailings facility capacity will be expanded in three lifts, with the first expansion scheduled for completion in January 2018 and two additional lifts to be completed approximately every two years thereafter.

Process Plant Equipment Procurement and Refurbishment

Aurizona is a brownfields project endowed with considerable existing infrastructure including access roads, a dedicated and reliable powerline, significant process plant equipment, offices, warehouses, laboratories, communications and a camp.

The plant design is based on a process plant capable of treating 8,000 tpd of ore through a combination of conventional gravity concentration and cyanide leach/CIP (carbon in pulp) processes. The design includes a new comminution circuit which comprises a primary jaw crusher, SAG (semi-autogenous grinding) mill, ball mill and pebble crusher. The jaw crusher and the mills have been ordered and delivery of the mills to site is expected during the second quarter.

Repairing, refurbishing and improving the existing process plant equipment resulted in cost efficiencies and a reduced construction timeline. There is also a large inventory of equipment on site that was either never commissioned or installed. Completing the installation and upgrades to existing equipment includes cyclones, the intensive leach reactor, three leach tanks, the high-rate thickener, and a new 12.5 MW (megawatt) main transformer as well as a new pressurized elution circuit and commissioning the carbon regeneration kiln. Refurbishing includes the CIP circuits, and additional improvements to the existing process plant includes upgrades to the cyanide destruction and tailings deposition system, gravity recovery circuit, electrical supply and distribution system, and instrumentation and controls. 

Detailed Engineering Activities

The project EPCM (engineering, procurement and construction management) work was awarded to Ausenco Engineering Canada Inc. (“Ausenco”) a diversified engineering, construction and project management company with extensive experience in the “fit-for-purpose” design and cost-effective construction of gold plants and mining projects globally, including a number of recent projects in Brazil.  Basic engineering has been substantially completed in Ausenco’s Vancouver office and detailed engineering work is being completed in Ausenco’s Belo Horizonte office.

Powerline

Aurizona has a dedicated and reliable powerline that connects to the Brazil electrical grid via the Maranhão power distribution utility, which provides access to low-cost power. Upgrades to two substations are required to support the increased power draw for the 8,000 tpd expansion. The substations are located at Manaus do Maranhão (46 km from Aurizona) and at the Aurizona plant site. 

CAUTIONARY NOTES AND FORWARD-LOOKING STATEMENTS

Neither the TSX Venture Exchange nor its Regulation Services Provider (as such term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

This document contains certain forward-looking information and forward-looking statements within the meaning of applicable securities legislation (collectively “forward-looking statements”). The use of the words “will”, “expected”, “objective”, “anticipated”, “underway” and similar expressions are intended to identify forward-looking statements. Forward-looking statements contained in this news release include, but are not limited to, statements regarding construction activities underway at Aurizona, the growth potential of the Company, anticipated production from the Aurizona Gold Mine and Castle Mountain Gold Mine, the Castle Mountain prefeasibility study, and the potential for other assets of the Company. Although the Company believes that the expectations reflected in such forward-looking statements and/or information are reasonable, undue reliance should not be placed on forward-looking statements since the Company can give no assurance that such expectations will prove to be correct. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements, including the risks, uncertainties and other factors identified in the Company’s periodic filings with Canadian securities regulators, and assumptions made with regard to the Company’s ability to complete construction at Aurizona and the timing to achieve production; the Company’s ability to complete construction within the approved budget; the Company’s ability to complete the Castle Mountain prefeasibility study and the results of the study; and the Company’s ability to achieve its expected growth and production potential. Furthermore, the forward-looking statements contained in this news release are made as at the date of this news release and the Company does not undertake any obligations to publicly update and/or revise any of the included forward-looking statements, whether as a result of additional information, future events and/or otherwise, except as may be required by applicable securities laws.